Shopfitting Projects
 |
Client: Loco Espresso |
Date: January 2010 |
Location: Ely |
| |
|
Premises: Coffee Shop |
Fitting time: 2 Days |
Our first installation of 2010 took place on a cold and snowy weekend of the 9th and 10th of January. The coffee shop located on the Ely train station platform had a new counter, several tegometall gondolas, a new raised suspended ceiling and 14 metres of wenge wall panelling fitted. |
 |
 |
Client: Lamorbey Wine |
Date: December 2009 |
Location: Sidcup |
| |
|
Premises: Wine Shop |
Fitting time: 1 Day |
Our final shopfit of a very busy 2009 was at a wine retailer in Sidcup, Kent. We designed built and installed 25 custom sized wine displays and a curved retail counter with lockable drawers. We also suppled 2 bottle chiller cabinets , all the printed headers and installed 3 panels of oak slatwall. The wine racks all have mini halogen lights fitted to the top to illuminate the wine bottles on display. The install was completed in a day and opened in time for Christmas and end of year sales. |
 |
 |
Client: Barbican Library |
Date: November 2009 |
Location: London |
| |
|
Premises: Library |
Fitting time: 2 Days |
One of our most visually impressive library installations has been completed at the Barbican Centre Library in the heart of London. The job entailed the manufacture and install of angled freestanding panels, wall mounted slatwall, a specialist LED lighting system, notice boards with leaflet holders, over 50 shelves, and 18 music browsers. Before the install we removed and disposed of all the existing units. The library image has been transformed completely and has given it an exciting and fresh new look. |
 |
 |
Client: Early Music Shop |
Date: November 2009 |
Location: London |
| |
|
Premises: Instrument Shop |
Fitting time: 1 Week |
Another shopfit took place this month, this time at the new Early Music Shop in Denmark Street London. Having outgrown their former premises as the London Recorder Centre they have taken up residence in the heart of Londons cultural music hub. We manufactured and installed new book displays, recorder displays and sheet music stands. |
 |
 |
Client: Frosts Brampton |
Date: November 2009 |
Location: Brampton |
| |
|
Premises: Garden Centre |
Fitting time: 1 Day |
One of our local projects in November was to build a false wall using slatwall at Frosts Garden Centre in Brampton. The wall consisted of 13 maple slatwall panels with aluminium inserts, edging trim and Tegometal wall uprights. The build took just under a day and gave the garden centre a new area to use as a clothing display wall. |
 |
 |
Client: Musicroom Portsmouth |
Date: November 2009 |
Location: Portsmouth |
| |
|
Premises: Sheet Music |
Fitting time: 2 Weeks |
We have just completed a 2 week shopfit of Musicrooms 17th store to open in the UK. The sheet music and instrument shop is located on Commercial Road in Portsmouth and will have a grand opening on 17th November 2009. The job entailed hanging over 70 sheets of maple and red slatwall, installing new carpet tiles, a logo printed entrance mat, toughened glass walls and new electrics and lighting. At International Displays we manufacture all our own browsers, counters and merchandise display stands. For this shopfit we produced and installed drum stick displays, recorder displays, sheet music browsers, glass showcases, and guitar displays. We hope the new store is a sucess for musicroom as they continue to expand across the UK. |
 |
 |
Client: Scorpion Shoes |
Date: November 2009 |
Location: Camden Town |
| |
|
Premises: Shoe Shop |
Fitting time: 1 Day / Night |
The proprietor of Scorpion Shoes, a high profile 3 storey shoe store in Camden Town approched us to provide a refit of their basement floor. The area required a complete facelift to bring it into line with the existing modern look and feel of the rest of the store. We cladded the walls in high gloss black laminated panelling and mounted the striking backlit white shoe display panels infront. All the units had illuminated headers at the top and safety backed mirror panels mounted in the bottom. We also supplied all the specially made pegs and ferrules to enable the display of the individual shoes. |
 |
 |
Client: Gwynned Libraries |
Date: October 2009 |
Location: Gwynned |
| |
|
Premises: Mobile Library |
Fitting time: 1 Day |
Gwynned Libraries have just launced a mobile information service for young people which will be visiting secondary schools in Gwynedd. The mobile Library Service will also be used it to visit primary schools to exchange books. This project involved the supply and install of red slatwall panels to hold various leaflets, and tables to hold two laptops so that youngsters can come into the van, collect information leaflets and access the website. All the panels were installed into their existing mobile van, which also included the individually printed header cards and graphics. |
 |
 |
Client: Cash Generator Preston |
Date: October 2009 |
Location: Preston |
| |
|
Premises: Pawn Brokers |
Fitting time: 2 Weeks |
Our 6th Cash Generator Shopfit has just been completed this time in Preston. The full installation from start to finish took 2 weeks. |
 |
 |
Client: Cash Generator Ellesmere Port |
Date: September 2009 |
Location: Ellesmere Port |
| |
|
Premises: Pawn Brokers |
Fitting time: 2 Weeks |
We have recently completed a 2 week shopfit of the latest Cash Generator franchise to open, this time in Ellesmere Port. All standard Cash Gen components were fitted all into the bare shell, completely renovating a derelict shop to a brand new and fully functioning retail store. As this project was underway, we were preparing to undertake another shopfit in Preston. |
 |
 |
Client: Bassaleg Post Office |
Date: September 2009 |
Location: Newport |
| |
|
Premises: Post Office |
Fitting time: 3 Days |
The proprietors of Bassaleg Post Office located near Newport, South Wales approached International Displays and asked us to undertake a refit of their local town Post Office. The re-fit encorporated the installation of over 20 maple slatwall panels, Tegometall bays, greeting card racks, acrylic shelving and shopfitting accessories. We also supplied a custom counter and a new shop door with security push button access. The installation took our team just 3 days to complete. |
 |
 |
Client: Music Room |
Date: August 2009 |
Location: Stratford |
| |
|
Premises: Sheet Music |
Fitting time: 1 Week |
One of our largest and most established customers Music In Print approached us to completely refit their sheet music store in Stratford Upon Avon. The re-fit which was completed mid August started by stripping out all the existing fixtures and fittings back to a basic shell. All new lighting, flooring, ceiling, electrics, and slatwall was installed in just 1 week. New book browers and sheet music browsers were also put into place. |
 |
 |
Client: Cash Generator Partick |
Date: July 2009 |
Location: Partick |
| |
|
Premises: Pawn Brokers |
Fitting time: 2 Weeks |
Our most recent Cash Generator shopfit has been completed, this time it was in Partick, Scotland. The 2 week install was completed on time and all the Cash Generator components feature as standard. Electrics, flooring, and ceiling were all part of the install, including reworking of existing space to maximise the retail area. Checking and buying counters are always present in Cash Generator stores and are complimented buy the jewellery cabinets and window displays all in corporate colours. |
 |
 |
Client: Country Collage |
Date: July 2009 |
Location: Ascot |
| |
|
Premises: Gift Shop |
Fitting time: 2 Days |
Country Collage is a small jewellery and gift shop located in Richmond Surrey. During the first week in July we undertook the refit of the store which included the installation of white slatwall, glass shelving, a new retail counter and a bespoke jewellery display. We also decorated the shopfront inside and out to give it a brand new look. |
 |
 |
Client: St.Marys Girls School |
Date: June 2009 |
Location: Ascot |
| |
|
Premises: School Shop |
Fitting time: 3 Days |
Towards the end of June we undertook a project to renovate an old laundry room at St.Marys girls school in Ascot and transform it into the school shop. The install consisted of a complete strip out and the installation of 20 maple slatwall panels, 4 glass display counters, Tegometal shelving with cupboards and a bespoke changing cubicle. The 3 day install was completed on time and the grand opening of the new school shop was undertaken to the delight of all the students. |
 |
 |
Client: Charity Shops |
Date: June 2009 |
Location: London |
| |
|
Premises: Charity Shop |
Fitting time: 2 Days |
Since the successful airing of the BBC2 television series 'Mary Queen of Charity Shops' we have been approached by several charity organisations and stores to help improve their image. From suppling simple bookcases and gondola units to complete shopfits encorporating slatwall and shelving, we have been able to makeover numerous high street stores and they have already reported an increase in turnover after only one weeks trading. We have worked with many names including The British Heart Foundation, Oxfam, The Shakespeare Hospice and Help the Aged. If you have a set budget and are looking for shop refit or image makeover then we are the right shopfitting company to help you. Contact us on 0844 257 8800 and speak to our sales team who can arrange an appointment to come out and visit your premises and discuss all the options available. |
 |
 |
Client: DAB International |
Date: June 2009 |
Location: Kent |
| |
|
Premises: London Golf Club |
Fitting time: 1 Day |
This years European Open Golf Tournament was held at the London Golf Club in Kent. We supplied, delivered and installed a hire stand consisting of 23 maple Freestanding Slatwall Units, 3 Counters, 2 H-Gondolas, several MDF merchandising tables, and various slatwall accessories. The official event merchandisers approched us and asked us to design and supply a stand to fit within their merchandising tents open to the public over the duration of the tournament. Setup of the stand commenced one week prior to the event and was completed in just one day, and breakdown and removal was completed in just 5 hours the day after the tournament finished. We are able to take care of all your hire stand requirements including design, supply and installation, if you have a show or event coming up soon then please contact us with your requirements. |
 |
 |
Client: Cash Generator Cheetham |
Date: April 2009 |
Location: Cheetham Hill |
| |
|
Premises: Pawn Brokers |
Fitting time: 2 Weeks |
Cheetham Hill in Manchester is the location of the latest Cash Generator franchise that has opened. The 2 week shopfit included all the usual components including laminated cash desks, security doors, glass display cabinets, slatwall, browsing shelves, and all carpets, electrics and ceiling. An added feature of this store is the mezzanine floor that we had to install that will be used as a stock room. |
 |
 |
Client: Cash Generator Neath |
Date: March 2009 |
Location: Neath |
| |
|
Premises: Pawn Brokers |
Fitting time: 2 Weeks |
Another shopfit for the Cash Generator franchise, this time in Neath, South Wales, has just been completed. During the 2 week install, all the usual components such as counters, slatwall, Tegometall shelving bays, gondolas and sliding glass door enclosures were installed. All flooring and electrics were also dealt with including aerial, CATV, CCTV and full test equipment bays. |
 |
 |
Client: Sheltons |
Date: February 2009 |
Location: Peterborough |
| |
|
Premises: Fishing Tackle |
Fitting time: 2 Weeks |
| The final shopfit of a very busy month for us was a local one at Sheltons of Peterborough Ltd - one of the largest fishing tackle retailers in the UK. Over 100 panels of maple slatwall were installed into thier 3000 sq. ft store, along with Tegometall Gondolas and wall runs. Special slatted lockable window displays were also created to allow the merchandise of product in the windows with easy access. The stairwell was also slatted along with 10 internal doors to provide maximum display space to the store which is planning a grand opening ceremony in March. |
 |
 |
Client: Dents Photo |
Date: February 2009 |
Location: Chesterfield |
| |
|
Premises:Photo Processing |
Fitting time: 1 Week |
| Continuing into February we completed another shopfit, this time for "Dents Photo" in Chesterfield. This project had a works duration of 1 week in which the store was completely gutted and refitted to spec. This included the fitting of new electrics, air conditioning units, a completely new staircase, new doors and also a new suspended ceiling. We also layed new carpet tiles, vinyl and lino throughout the store. The display components consisted of Tegometall gondolas and wall bays, glass display units, slatwall, and custom made storage counters. We also manufactured and supplied the main counter which included a gate flap for access. Additional to the shopfit we supplied all the display accessories and glass shelving. Alongside all our own work we also project managed all the contractors supplied by the client for the alarm, phone and plumbing requirements. |
 |
 |
Client: The Green Bottle |
Date: February 2009 |
Location: Bucks |
| |
|
Premises: Wine Shop |
Fitting time: 3 Days |
| An extremely busy February included the shopfit of a new wine shop "The Green Bottle". This wine shop is located in the small village of Chalfont St.Giles, and was completed over a 3 day period. The fit out included 30 bespoke made wine display units, several slatwall panels installing and a custom shaped laminated counter with built in cupboards. We also installed a new glazed front door and supplied all the header cards and graphics for the inside of the store. |
 |
 |
Client: Cash Generator Northampton |
Date: February 2009 |
Location: Northampton |
| |
|
Premises: Pawn Brokers |
Fitting time: 1 week |
| The Cash Generator franchise is well known all over the UK and our first full shopfit was undertaken at the Northampton store in mid February. The distinctive yellow and blue corporate colour scheme is a hallmark of their "pawn broker" shops and this was achieved by using coloured slatwall and powder coated metal work. The whole shopfit took 2 weeks to complete, and included custom lockable glass cabinets, all doors with electronic entrance keypads, sliding glass for the customer counter areas and all flooring and lighting. We are now working on numerous other franchises over the UK with several more shopfits due to take place soon. |
 |
 |
Client: Burwell Post Office |
Date: January 2009 |
Location: Newmarket |
| |
|
Premises: Post Office |
Fitting time: 2 days |
| 2009 begun with a shopfit of Burwell Post Office in Cambridgeshire. The small village post office was completely stripped out and maple slatwall installed to all walls. Several Tego bays and gondola units were also supplied along with shelving and acrylic card units. 3 Greeting card and gift wrap units were fitted to replace the existing aging displays and provide the shop with a new clean look. The install was completed in just 2 days to ensure minimal disruption to business. |
 |
 |
Client: Pounds Around |
Date: October 2008 |
Location: Dudley |
| |
|
Premises: Pawn Brokers |
Fitting time: 3 days |
| A very busy November ended with a new shopfit for pawn shop Pounds a Round in Dudley. The striking yellow colour scheme is very eye catching and compliments the type of items on sale. Over 20 panels of slatwall with matching edging trim was hung and various slatwall metal shelving supplied in the same yellow colour. We also installed Tegometall, window glass shelving and three bespoke counters. The job took three men just three days to complete which also included the laying of a new flooring carpet tiles. |
 |
 |
Client: Mailboxes Etcetera |
Date: October 2008 |
Location: Mill Hill |
| |
|
Premises: Mailbox Rental |
Fitting time: 2 days |
| Within 14 days of first contact with us the shopfit for Mailboxes Etc has been fully completed. From the initial site visit and quick quote turnaround our team of four men took just two days to totally refit the premises. 38 panels of slatwall have been installed along with Tegometall uprights and several island gondola units. The job also consisted of installing extra spot lights into the window, adjusting the existing counter, removing the low level studwall and remounting existing cupboards in the back area of the store. The owner of the shop is so pleased with his new store he has already recommended us to head office. |
 |
 |
Client: Moulton College Pet Centre |
Date: October 2008 |
Location: Northampton |
| |
|
Premises: Pet and Garden |
Fitting time: 2 days |
| During October we installed a set of Tegometall bays with slatwall back panels into the newly built Moulton College Garden and Pet Centre. We also designed and built several island counter units to compliment the stores image and supplied many different sizes of slatwall glass shelving. Due to the nature of the wooden building nothing could be screwed to the walls, this is where Tegometall comes into its own as it is used freestanding but still keeps the versatility of slatwall. |
 |
 |
Client: Cash Convertors |
Date: October 2008 |
Location: Grays |
| |
|
Premises: Pawn Brokers |
Fitting time: 3 days |
| The Cash Convertors in Grays, Essex, refit consisted of ripping out the contents of the existing shop before installing slatwall, Tegometall and several glazed showcase units. The 3 day shopfit also included the manufacture and install of a new counter unit and a laying a new floor. |
 |
 |
Client: Assembly of God |
Date: September 2008 |
Location: London |
| |
|
Premises: Bookshop |
Fitting time: 2 days |
| During a busy month we fitted out a new Christian bookshop in London. The complete fit-out consisted of installing maple slatwall panels throught the store and supplying a combination of both glass and wooden cabinets. The shopfit took 2 days to complete and transformed a bare carcass of a room into a fully fitted retail bookstore. |
 |
 |
Client: Banks of York |
Date: August 2008 |
Location: York |
| |
|
Premises: Music Store |
Fitting time: 4 weeks |
| Our most expansive project to date was undertaken at Banks of York, the countries largest sheet music and instrument store. The 3 floor shopfit took around 4 months of planning and CAD to ensure the desired result was achieved at miniumum disruption to the store which needed to keep trading during the install. Over 4500 sq ft across the 3 floors was completely renovated including flooring, ceiling, electrics, stairwells and rails. |
 |
 |
Client: Movie Mix |
Date: July 2008 |
Location: Ilfracombe |
| |
|
Premises: DVD Rental |
Fitting time: 1 week |
| The beginning of July saw us complete another week long shop fit, this time it was a DVD and movie store based in Ilfracombe North Devon. International Displays completely gutted the existing store and laid new flooring, installed a new ceiling and re wired the electrics. The main transformation was acheived by installing slatwall around the whole of the store in an eyecatching white and red colour scheme. |
 |
 |
Client: The Smiling Grape |
Date: June 2008 |
Location: St. Neots |
| |
|
Premises: Wine Shop |
Fitting time: 2 weeks |
A new local company, The Smiling Grape Company, opened their first retail wine shop in St.Neots, Cambridgeshire.
International Displays won the contract to refit the grade 2 listed building from top to bottom including a full re wire, new floor, external and internal signage and a range of bespoke oak units finished off with a 1800mm square wall mural of a vineyard in Spain. The job was completed over a 2 week period. |
 |
 |
Client: Music Room |
Date: May 2008 |
Location: Norwich |
| |
|
Premises: Music Shop |
Fitting time: 2 days |
| New slatwall and several vinyl, and sheet music browsers were installed in the Music Room in a 48 hour shopfit. 2 teams of men worked non stop to ensure minimum downtime to the music retailers business. This is one of many stores we have re-fitted for the Music Room around the UK. The colour scheme on this shopfit centered around maple and aluminium and the browsers were fitted to enable maximum display of music books and ability to display items through the window. |
 |
 |
Client: Atlantis Caps |
Date: May 2008 |
Location: London |
| |
|
Premises: Clothes Shop |
Fitting time: 8 hours |
| One of International Displays' smaller refits brought a fair few challenges. A 3 metre x 2 metre mezzanine floor on Oxford Street London was slatwall clad and bespoke cupboards and mirrors were added to give a stylish finish to a baseball cap concession. The shop was finished in 8 hours despite massive parking and access restrictions. |
 |
 |
Client: Nite Out |
Date: April 2008 |
Location: Aberdeen |
| |
|
Premises: Party Shop |
Fitting time: 4 days |
| Successful adult chain Nightlife recently opened their first party accessories store in Aberdeen. The Nite Out shop was a 4 day fit out by International Displays which included the laying of a new oak laminate floor, electrical and plumbing work, external signage and all internal fixtures and fittings. The job also entailed installing 25 sheets of slatwall with aluminium inserts and a new counter matching the shops colour scheme. |
 |
 |
Client: Jaysons |
Date: March 2008 |
Location: Birmingham |
| |
|
Premises: Music Shop |
Fitting time: 5 days |
| In March, Jaysons store in Birmingham knocked through into a back room and doubled the size of his retail space. International Displays won the contract to refit the newly sized store using 62 sheets of white slatwall with inserts. We also installed Tegometall bays, 11 bespoke glass cabinets, over 100 multimedia shelves and a 14 metre glass and aluminium counter. The fit was completed over 5 days and the store re-opened within 2 weeks. |
 |
 |
Client: Hawleys |
Date: March 2008 |
Location: Dartford |
| |
|
Premises: Garden Centre |
Fitting time: 4 days |
| We completed the refit and refurbishment of three sections of the Hawley Garden Centre in Dartford. The project consisted of renovating the gift, stationary and store room sections by installing slatwall to all areas. This was a particularly complicated job due to the nature of the glass buildings used in garden centres, so a lot of stud work had to be carried out prior to the installation of the slatwall. |
 |
 |
Client: Frosts |
Date: September 2007 |
Location: Frilford |
| |
|
Premises: Garden Centre |
Fitting time: 2 days |
The beginning of this month saw another Frost's Garden Centre shop fit completed, this time it was their Millets Farm outlet. The 2800 sq ft installation consisted of 41 slatwall and tegometall gondola's, as well as over 40 slatwall and windows units. The installation was completed in just 2 days, thus minimizing disruption to their existing trade.
|
 |
 |
Client: PMS International |
Date: June 2007 |
Location: Basildon |
| |
|
Premises: Toys and Gifts |
Fitting time: 15 days |
This month we undertook one of our largest projects to date with the fitting of the new showroom at PMS International. The 12,500 sq ft showroom had over 700 panels of slatwall fitted and a huge range of gondola units manufactured and installed. |
 |
 |
Client: Music Room |
Date: May 2007 |
Location: Salisbury |
| |
|
Premises: Music Shop |
Fitting time: 10 days |
May was another busy month for International Displays with several shopfittings taking place. The Music Room in Salisbury had a complete re-fit and we undertook the whole project from start to finish which included designing and installing the custom built displays, furniture and browsers as well as all the lighting and counters. |
|
|
|